Coffey has completed the upgrade of the chlorine dosing system at Kilminchy Water Treatment Plant in Portlaoise, Co. Laois, on behalf of Uisce Éireann, as part of the Water Treatment Plant Upgrade Framework for the East Midlands Region.
The project involved replacing the existing chlorine gas dosing system with a new sodium hypochlorite dosing system, providing separate dosing arrangements for raw water oxidation and filtered water disinfection.




The scope of works included:
• Installation of a new chemical dosing kiosk incorporating a 5,000-litre sodium hypochlorite bulk storage tank, day tanks and duty/standby dosing pumps.
• Installation of above-ground stainless steel pipework incorporating a flowmeter and chemical dosing points.
• Installation of associated chemical dosing equipment and electrical infrastructure.
• Integration of the new dosing system with existing plant instrumentation and control systems.




The upgrade was designed to minimise disruption to the existing treatment processes while supporting the continued operation of the water treatment plant, which serves Portlaoise and surrounding areas.
The completed works provide an alternative to chlorine gas dosing, supporting the long-term operation and reliability of the facility.