𝐃𝐞𝐥𝐠𝐚𝐧𝐲 𝐭𝐨 𝐁𝐥𝐚𝐜𝐤𝐥𝐢𝐨𝐧 𝐂𝐡𝐚𝐩𝐞𝐥 𝐑𝐨𝐚𝐝 𝐈𝐦𝐩𝐫𝐨𝐯𝐞𝐦𝐞𝐧𝐭 𝐒𝐜𝐡𝐞𝐦𝐞 | 𝐏𝐫𝐨𝐣𝐞𝐜𝐭 𝐔𝐩𝐝𝐚𝐭𝐞

Coffey is continuing to make progress on the 𝐃𝐞𝐥𝐠𝐚𝐧𝐲 𝐭𝐨 𝐁𝐥𝐚𝐜𝐤𝐥𝐢𝐨𝐧 𝐂𝐡𝐚𝐩𝐞𝐥 𝐑𝐨𝐚𝐝 𝐈𝐦𝐩𝐫𝐨𝐯𝐞𝐦𝐞𝐧𝐭 𝐒𝐜𝐡𝐞𝐦𝐞, a project that will support safer, more connected travel for the local community.

𝐒𝐞𝐜𝐭𝐢𝐨𝐧 1 is now substantially complete. Recent works include a new HRA asphalt ramp at the entrance to Littlebrook Estate, along with finished driveway and side road tie-ins. This builds on the earlier reopening to two-way traffic and the delivery of improved pedestrian and cycling facilities.

𝐒𝐞𝐜𝐭𝐢𝐨𝐧 2 is advancing well, with the current focus on accommodation works and utility infrastructure. Key milestones include:

● Nearing completion of wall construction and stone masonry, including c.300m of stone-faced retaining and block walls.

● Installation of 200m of drainage and sewer infrastructure at depths up to 3.5m.

● Over 7km of new utility ducting installed.

● New ESB infrastructure now live, with all properties transferred to the new network and redundant poles removed.

● Installation of new public lighting columns along the route.

● Completion of new 350m watermain, with property connections now completed.

We’re working closely with utility providers to coordinate the transition to new networks, enabling the safe removal of existing services ahead of road construction.

This project is a vital step in enhancing local infrastructure, with phased delivery continuing through to mid-2026.